New Saint Peter Parish Hall

click here for webcam live feed

4/30/2017 – Lots of progress being made now! All steel is erected and roof decking is in place. Rough coat of auxiliary parking lot has been laid. The finish or top coat and striping will not occur until almost the very end of the project. The finish coat will make it possible for us to use the auxiliary parking lot for carnival parking!
“Framing” of meeting rooms, bathrooms and indoor kitchen is completed. Also completed is the ‘hidden’ work of underground piping for runoff from roof downspouts and courtyard. On Tuesday, May 9, at our regularly scheduled “contractors meeting” we will finalize plans for the playground equipment to be installed in the courtyard. The contractor has supplied images of the planned equipment and these can be seen in the hallways leading to the office and meeting rooms. Prayer for the success of the project is much appreciated. Pray not just for good weather and safe construction, but also for wise planning for the use of the parish hall beginning next fall.
What type of event should we have to open the new parish hall? Send you suggestions to the Parish Pastoral Council at stpeterchesco@comcast.net.

4/18/2017 – Steel arrived – beams are set into place

 

 

 

 

 

3/19/2017 – Update:

The weather during construction has been extraordinary!  Our builder, Gardner Fox, has established August 28 as the date for the finishing of the project.
Beginning this week the parking lot addition (required by the township) will make significant progress as concrete curbing is installed and the parameters of the parking lot become more evident.  The additional parking area will provide 153 more parking spaces.  This complies with, and even exceeds, the required number of parking spaces relative to the seating capacity of the parish hall (275 people for a sit down dinner).
Underground plumbing connections, for the indoor kitchen, the café, and the bathrooms, are set at the parish hall site and nearly 100% of concrete “footers and foundations” are poured.  These achievements were possible in such a timely manner because of the mild winter. Amazing progress is possible because of workable soil for digging, excavating, and moving materials into place.
A big factor for both parish hall location and the additional parking area is the planning from 10 years ago.  Both sites were in such favorable stages of preparation allowing implementation of rapid mobilization and construction stages.  Soon gravel sub base will be installed for the parish hall pad and for the parking area.  By April 17 (the week after Easter) we will see steel installation.  Work will move very rapidly from then on as walls will be built and roofing can be installed.

February 2017 – Update:

Construction is scheduled to take 210 working days, about 7 months. If all goes well we can plan for hall completion by September of 2017. In general the parish hall construction will include a large parish hall with banquet/event seating for 275 persons. The building will include a separate section of additional meeting space, additional restrooms, and an indoor kitchen facility designed by Singer Equipment Supply located at 150 S. Twin Valley Road, Elverson, PA 19520 (singerequipment.com.) The indoor kitchen will include a six unit electric range, electric convection oven, food warming/food holding cabinets, a 3 compartment sink and separate hand washing station, an ice maker, freezer and separate refrigerators, several work tables/preparation tables, and an exhaust system.

Additional parking is being constructed across the loop road, and adjacent to the Pope John Paul II Catholic School property, providing 155 additional parking spaces. The new parking area will be well lighted and landscaped in accord with West Brandywine Township requirements.Parish Hall planning

1/10/2017 – Update: 

All township approvals, construction planning and financing are in place.  Throughout late November and all of December we have been negotiating the stipulations placed on the project by the Archdiocese.  Some of the stipulations were known to us from the original approval of Archdiocesan College of Consultors (June 24, 2016).  These included arranging of funding and possible bank loans, providing a 5-year budget plan, completing and submitting for review 100% complete building plans and completing all governmental (Township) approval processes. At a certain point, several Archdiocesan stipulations not previously articulated stopped the process and delayed the start of construction.  We are very close to breaking ground on this long-awaited project!

10/16/2016 – Parish Hall Construction: We have more progress to report regarding construction of the parish hall.  The West Brandywine Planning Commission and the Board of Supervisors have approved the most recent version of our Parish Hall plans.  Several financial institutions have expressed interest in offering a “Term Sheet” for the project.  The builder, Gardner Fox, has delivered final plans to the parish.

What more needs to be done?  The Archdiocesan Legal Services Office, theconstruction-trailer-arrives Parish Financial Support and Service Office, and the Office for Property Services and Real Estate will have to approve all the construction documents and financing plans.  Also, a building permit will have to be issued by the Township.

The parish will soon see a construction trailer on the site and some Gardner Fox signs directing vehicles to and from the site.  Surveyor stakes and silt fences will also likely appear on the property, signaling preparations for the project to begin.  It is beginning to look like we may be ahead of schedule for our February 30 groundbreaking!

July 2016 – We are pleased to announce the impending Saint Peter Parish Hall: On Friday, June 24, 2016, Archbishop Chaput approved our plans for the construction of Saint Peter Parish Hall.

In the 10 years since the move from our original site and construction of the permanent Saint Peter Church building, we have succeeded in saving significant funds for the completion of the parish hall. We express sincer
e thanks to all who have participated in supporting the vision of a parish hall.

The archdiocese expressed its appreciation to our parish leadership, specifically the Parish Finance Council and Parish Pastoral Council for their dedication to the mission and vision of the parish.  The professional financial projections our Finance Council offered were very helpful to the College of Consultors and the Archbishop.  Cited very specifically was the strong financial support of our parishioners in meeting our debt reduction obligations over the past ten years, as well as the excellent fiscal management and accurate timely financial reporting of our parish leadership.
The parish hall will need to accommodate Faith Formation programs and processes for all our parish families.  The ChristLife programs (Discovering Christ, Following Christ and Sharing Christ), RCIA and family faith formation processes will flourish in the new facility. A well-landscaped, secure, outdoor kitchen facility with grills, ovens and sinks will support youth and family activities.  Parish groups will be able to function with greater flexibility and broader programming using both the outdoor facility and the indoor “caterers” kitchen.

The design of the hall finishes the third side of the existing courtyard and a covered portico will help enclose the courtyard connecting the front of the church with the hall.  The facility will be totally accessible for those with disabilities.  Additional restroom facilities and storage are also a part of the planned construction.